DMCI Homes Preselling Projects | February 2016 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

Verawood Residences

Building completion: February 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
Verawood Residences February 2016 Construction update: Marsala (left) – 100%. All floors completed. Accepted by QMD. Dressed up all units. Peridot (middle) – 98.10%. All floors completed. Accepted by QMD. Ongoing dress up of units. Canary (right) – 91.19%. All floors completed. Ongoing QMD acceptance. Ongoing dress up of units.
Verawood Residences February 2016 Construction update: Flamingo – 54.70%. All floors completed. Structural works completed. Ongoing masonry works.
Verawood Residences February 2016 Construction update: Aqua – 62.97%. All floors completed. Ongoing bare units.
Verawood Residences February 2016 Construction update: Overall project completion – 80.02%. Wisteria (right) – 100%. All floors completed. Accepted by QMD. Dressed up all units. Lime (middle) – 49.46%. All floors completed. Structural works completed. Ongoing masonry works.

Outlook Ridge Residences

Building completion: June 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, BRISTLE RIDGE, the newest mid-rise preselling development similar to OUTLOOK RIDGE RESIDENCES in Baguio is now open for selling!
Outlook Ridge Residences February 2016 Construction update: Front Elevation. Over-all project completion: 97.38%. North wing level: Structural and Masonry – 100%. Finishing – 100%. On-going QMD inspection.
Outlook Ridge Residences February 2016 Construction update: Rear Facade. South wing level : Structural and Masonry – 100%. Finishing – 85%. On-going finishing works.
Outlook Ridge Residences February 2016 Construction update: Mid deck. On-going finishing works.
Outlook Ridge Residences February 2016 Construction update: Roof deck
Outlook Ridge Residences February 2016 Construction update: Atrium
Outlook Ridge Residences February 2016 Construction update: Atrium

Levina Place

Building completion:

  • Selene Building – October 2016
  • Callista Building – July 2016
  • Amalthea Building – Feb 2017
Levina Place January 2016 Construction update: Clubhouse
Levina Place January 2016 Construction update: Selene building
Levina Place January 2016 Construction update: Selene building atrium
Levina Place January 2016 Construction update: Selene building atrium
Levina Place January 2016 Construction update:

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why,IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
The Birchwood February 2016 Construction update: Alder building
The Birchwood February 2016 Construction update: Clubhouse
The Birchwood February 2016 Construction update: Over-all view of the site

Asteria Residences

Building completion:

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
  • Lucerne – April 2018
  • Begonia – June 2018
  • Heather -TBA
  • Cercis – TBA
Asteria Residences February 2016 Construction update: Vinca building : Structural – 100%. Over-all project completion : 17%.
Asteria Residences February 2016 Construction update: Nerine building : Structural – 44.44%.
Asteria Residences February 2016 Construction update: Mimosa building : Structural – 33.33%.
Asteria Residences February 2016 Construction update: Lucerne building : Structural – 22.22%.
Asteria Residences February 2016 Construction update: Heather building : Structural – 12.50%.
Asteria Residences February 2016 Construction update: Begonia building: Structural – 25%.

Mirea Residences

Building completion:

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – February 2018
  • Selenia – August 2018
  • Solana – February 2019
  • Antara – April 2019
  • Marinda – June 2019
  • Aleia – TBA
Mirea Residences January 2016 Construction update
Mirea Residences January 2016 Construction update
Mirea Residences January 2016 Construction update

Zinnia Towers

Building completion:

  • North Tower: May 2016
  • South Tower: September 2017
Zinnia Towers January 2016 Construction update

Viera Residences

Building completion: March 2018

Viera Residences Feb 2016 Construction update: Overall Completion – 46%
Viera Residences Feb 2016 Construction update: Overall Completion – 46%
Viera Residences Feb 2016 Construction update: Swimming Pool – 38%
Viera Residences Feb 2016 Construction update: Finishing (ongoing at ground floor and mezzanine) – 6.5%
Viera Residences Feb 2016 Construction update: Finishing (ongoing at ground floor and mezzanine) – 6.5%

Lumiere Residences

Building completion:

  • East Tower: October 2018
  • West Tower:  June 2019
  • North Tower: November 2020
Lumiere Residences February 2016 Construction update: East Tower: Structural – 71.05%, Masonry – 27.90%. On-going structural works on the 28th floor. West Tower: Structural – 71.05%. Masonry – 25.40%. On-going structural works on the 28th floor. North Tower: On-going excavation; preparation of retaining wall.
Lumiere Residences February 2016 Construction update: Atrium
Lumiere Residences February 2016 Construction update: Lounge area

Brio Tower

Building completion: November 2019

Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1

Sheridan Towers

Building completion:

  • South Tower -November 2018
  • North Tower -February 2020
Sheridan Towers February 2016 Construction update

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.

Other DMCI Homes’ resort-type projects:

Previous post

LUMIERE RESIDENCES Open House On March 12, 2016

Next post

DMCI Homes named one of Mandaluyong City’s top taxpayers in 2015