DMCI Homes Preselling Projects | June 2017 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top, trusted and reliable developer always gives updates on your investments!

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
The Birchwood June 2017 Construction update: Evergreen building
The Birchwood June 2017 Construction update: Maple building
The Birchwood June 2017 Construction update: Jogging path
The Birchwood June 2017 Construction update: Clubhouse

Mirea Residences

Building completion:

  • Maia – February 2017
  • Sitara – April 2017
  • Vespera – July 2017
  • Selenia September 2017
  • Solana – November 2017
  • Antara – February 2018
  • Marinda – May 2018
  • Aleia – August 2018
Mirea Residences June 2017 Construction update: Sitara building
Mirea Residences June 2017 Construction update: Pool complex
Mirea Residences June 2017 Construction update: Marinda building
Mirea Residences June 2017 Construction update: Aleia building

Asteria Residences

Building completion:

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
  • Lucerne – April 2018
  • Begonia – June 2018
  • Heather -August 2018
  • Cercis – November 2018
Asteria Residences June 2017 Construction update: Nerine building
Asteria Residences June 2017 Construction update: Clubhouse
Asteria Residences June 2017 Construction update: Playground
Asteria Residences June 2017 Construction update: Pool area
Asteria Residences June 2017 Construction update: Pool area
Asteria Residences June 2017 Construction update: Basketball court

Zinnia Towers

Building completion:

  • North Tower: Ready for occupancy
  • South Tower: September 2017
Zinnia Towers June 2017 Construction update
Zinnia Towers June 2017 Construction update: Garden atrium
Zinnia Towers June 2017 Construction update: Open lawn
Zinnia Towers June 2017 Construction update: Roof deck
Zinnia Towers June 2017 Construction update: Sky lounge
Zinnia Towers June 2017 Construction update: Sky patio
Zinnia Towers June 2017 Construction update

Viera Residences

Building completion: October 2017

Viera Residences June 2017 Construction update
Viera Residences June 2017 Construction update
Viera Residences June 2017 Construction update: Lobby
Viera Residences June 2017 Construction update: Ground lobby
Viera Residences June 2017 Construction update: Kiddie pool
Viera Residences June 2017 Construction update: Lap pool
Viera Residences June 2017 Construction update: Walkway
Viera Residences June 2017 Construction update: Landscaped atrium
Viera Residences June 2017 Construction update: Landscaped atrium
Viera Residences June 2017 Construction update: Garden atrium
Viera Residences June 2017 Construction update: Roof deck
Viera Residences June 2017 Construction update: Roof deck

Brio Tower

Building completion: July 2018

Brio Tower June 2017 Construction update

Fairway Terraces

Building completion: February 2019

Fairway Terraces June 2017 Construction update

Sheridan Towers

Building completion:

  • South Tower -November 2017
  • North Tower -February 2020
Sheridan Towers June 2017 Construction update: South Tower
Sheridan Towers June 2017 Construction update: South Tower
Sheridan Towers June 2017 Construction update: South Tower
Sheridan Towers June 2017 Construction update: North Tower

Lumiere Residences

Building completion:

  • East Tower: October 2017
  • West Tower:  June 2018
  • North Tower: November 2020
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates: East Tower
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates: West Tower
Lumiere Residences June 2017 Construction updates: North Tower
Lumiere Residences June 2017 Construction updates: Link bridge
Lumiere Residences June 2017 Construction updates: Pool area
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates
Lumiere Residences June 2017 Construction updates

Ivory Wood

Building completion:

  • Anahaw -May 2018
  • Palmira – October 2018
  • Lauan – October 2018 
  • Kamia – April 2019
  • Flores – June 2019
  • Adelfa – August 2019
  • Abaca – November 2019 
Ivory Wood June 2017 Construction update: Clubhouse
Ivory Wood June 2017 Construction update: Pool area
Ivory Wood June 2017 Construction update: Pool area
Ivory Wood June 2017 Construction update: Pool area
Ivory Wood June 2017 Construction update: Pool area
Ivory Wood June 2017 Construction update: Entrance gate
Ivory Wood June 2017 Construction update: Clubhouse
Ivory Wood June 2017 Construction update
Ivory Wood June 2017 Construction update: Palmira building

Torre de Manila

Building completion: January 2020

Torre de Manila June 2017 Construction update
Torre de Manila June 2017 Construction update

Brixton Place

Building completion:

  • Brent – September 2021
  • Weston – May 2022
Brixton Place June  2017 Construction update

The Celandine

Building completion: October 2021

The Celandine June 2017 Construction update

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.