DMCI Homes Preselling Projects | March 2016 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

Verawood Residences

Building completion: February 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
Verawood Residences March 2016 Construction update: Canary Building – 94.19% (All floors completed, Unit dress-up ongoing)
Verawood Residences March 2016 Construction update: Aqua Building – 71.56% (All floors completed, Finishing works ongoing)
Verawood Residences March 2016 Construction update: Flamingo building – 59.10% (All floors completed, Masonry works ongoing)
Verawood Residences March 2016 Construction update: Lime building – 51.92% (All floors completed, Exterior canopy works ongoing)

Outlook Ridge Residences

Building completion: June 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, BRISTLE RIDGE, the newest mid-rise preselling development similar to OUTLOOK RIDGE RESIDENCES in Baguio is now open for selling!
Outlook Ridge Residences March 2016 Construction update: Overall Project Completion – 97.63%
Outlook Ridge Residences March 2016 Construction update: South Wing – Finishing works 85%
Outlook Ridge Residences March 2016 Construction update: Mid Deck – 100% Complete
Outlook Ridge Residences March 2016 Construction update: North Wing – 100% Complete
Outlook Ridge Residences March 2016 Construction update: Roof Deck – 100% Complete

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
The Birchwood March 2016 Construction update: Alder building – 67%
The Birchwood March 2016 Construction update: Evergreen building – 40%
The Birchwood March 2016 Construction update: Oleander building – 33%
The Birchwood March 2016 Construction update: Maple building (left) – 26%, Calathea building (right) – 11%
The Birchwood March 2016 Construction update: Clubhouse – 63%

Asteria Residences

Building completion:

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
  • Lucerne – April 2018
  • Begonia – June 2018
  • Heather -TBA
  • Cercis – TBA
Asteria Residences March 2016 Construction update: Vinca building – Structural works 100%, Masonry 65%
Asteria Residences March 2016 Construction update: Nerine building – Structural works 96.3%
Asteria Residences March 2016 Construction update: Begonia building – Structural works 25%
Asteria Residences March 2016 Construction update: Heather building- Structural works 12.50%
Asteria Residences March 2016 Construction update: Mimosa building – Structural works 33.33%

Mirea Residences

Building completion:

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – February 2018
  • Selenia – August 2018
  • Solana – February 2019
  • Antara – April 2019
  • Marinda – June 2019
  • Aleia – TBA
Mirea Residences March 2016 Construction update: Guard House and Entrance Gate – Structural 100%, Overall Completion 13%
Mirea Residences March 2016 Construction update: Maia Building – Structural 100%, Overall 29%
Mirea Residences March 2016 Construction update: Sitara Building – Structural 73%, Overall 14%
Mirea Residences March 2016 Construction update: Clubhouse – Structural 10%, Overall Completion 5%
Mirea Residences March 2016 Construction update: Amenity area
Mirea Residences March 2016 Construction update: Vespera Building – Structural 31%, Overall – 9%

Zinnia Towers

Building completion:

  • North Tower: May 2016
  • South Tower: September 2017
Zinnia Towers March 2016 Construction update: North Tower – Structural 100%, Masonry 100%, Finishing 89%
Zinnia Towers March 2016 Construction update: South Tower – Structural 60%, Masonry 30%, Finishing 4%
Zinnia Towers March 2016 Construction update: Swimming Pool – 100%
Zinnia Towers March 2016 Construction update: Roof Deck (North Tower) – 98%

Lumiere Residences

Building completion:

  • East Tower: October 2018
  • West Tower:  June 2019
  • North Tower: November 2020
Lumiere Residences March 2016 Construction update: East Tower (back) – Structural 76.32%, Masonry – 33.76%, Finishing (Bare) – 13.16%
Lumiere Residences March 2016 Construction update: West Tower (left) – Structural 76.32%, Masonry – 29.95%, Finishing (Bare) – 13.16%

Viera Residences

Building completion: March 2018

Viera Residences March 2016 Construction update: Overall Completion – 46%
Viera Residences March 2016 Construction update: Overall Completion – 46%
Viera Residences March 2016 Construction update: Swimming Pool – 38%
Viera Residences March 2016 Construction update: Finishing (ongoing at ground floor and mezzanine) – 6.5%

Brio Tower

Building completion: November 2019

Brio Tower March 2016 Construction update: Structural (ongoing works on 2F and 3F) – 38%
Brio Tower March 2016 Construction update: Structural (ongoing works on 2F and 3F) – 38%
Brio Tower March 2016 Construction update: Masonry (ongoing works on basement 1-5) – 3%
Brio Tower March 2016 Construction update: Playground (structural works complete) – 34%
Brio Tower March 2016 Construction update: Swimming Pool (structural works complete) – 39%

Sheridan Towers

Building completion:

  • South Tower -November 2018
  • North Tower -February 2020
Sheridan Towers March 2016 Construction update: South Tower – Masonry 47% (On-going construction on the 40th floor)
heridan Towers March 2016 Construction update: North tower – Structural works 88%

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.