DMCI Homes Preselling Projects | November 2015 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

One Castilla Place

Building completion: January 2016

One Castilla Place Novemebr 2015 Construction update: Finishing Works: 84.50% On-going painting of hallways and building facade
One Castilla Place Novemebr 2015 Construction update: Finishing Works: 84.50%.
One Castilla Place Novemebr 2015 Construction update: Finishing Works: 84.50%.
One Castilla Place Novemebr 2015 Construction update: Finishing Works: 84.50%.

Outlook Ridge Residences

Building completion: June 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, BRISTLE RIDGE, the newest mid-rise preselling development similar to OUTLOOK RIDGE RESIDENCES in Baguio is now open for selling!
Outlook Ridge Residences October 2015 Construction update: Over-all Site Development – 78%.
Outlook Ridge Residences October 2015 Construction update: North Wing – 77.18%. 7/7 Levels are concreted ; South Wing – 65.23%. 7/7 Levels are already concreted.
Outlook Ridge Residences October 2015 Construction update: Sky deck.
Outlook Ridge Residences October 2015 Construction update: Atrium.

Levina Place

Building completion:

  • Selene Building – October 2016
  • Callista Building – July 2016
  • Amalthea Building – Feb 2017
Levina Place October 2015 Construction update
Levina Place October 2015 Construction update
Levina Place October 2015 Construction update

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling development similar to Verawood Residences in Taguig are now open for selling!
The Birchwood October 2015 Construction update: Guardhouse: 82.50%. On-going finishing works.
The Birchwood October 2015 Construction update: Alder : 36.25%. On-going Masonry Works at Exterior Rear Wing.
The Birchwood October 2015 Construction update: Over-all construction status of the site : 24.45%.
The Birchwood October 2015 Construction update: Evergreen : 30.00%. On-going installation of rebars and formworks for Parapet Walls at RD.
The Birchwood October 2015 Construction update: Oleander : 12.90%. On-going installation of rebars and formworks for Columns. Maple : 7.50%. Concreting of Parking Level 1 Suspended Slabs. ; Calathea : 7.50%. Concreting of Parking Level 1 Suspended Slabs.

Asteria Residences

Building completion:

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
  • Lucerne – April 2018
  • Begonia – June 2018
  • Heather -TBA
  • Cercis – TBA
Asteria Residences October 2015 Construction update: Mimosa – Structural Works 2 out of 9 Floors = 22%
Asteria Residences October 2015 Construction update: Begonia – Structural Works: 1 out of 8 Floors = 12%
Asteria Residences October 2015 Construction update: Heather – Structural Works: 0 out of 8 Floors = 0%

Mirea Residences

Building completion:

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – February 2018
  • Selenia – August 2018
  • Solana – February 2019
  • Antara – TBA
  • Marinda – TBA
  • Aleia – TBA
Mirea Residences October 2015 Construction update
Mirea Residences October 2015 Construction update

Zinnia Towers

Building completion:

  • North Tower: May 2016
  • South Tower: September 2017
Zinnia North Tower November 2015 Construction update: Masonry Works 90.71% complete; On-going punchlist works at 38th floor; Finishing Works 70.45% complete; Turn Over Group acceptance of bare units at 37th floor
Zinnia South Tower Novemebr 2015: Structural Works 38.78% on-going 19th floor; Masonry Works: 3.05% on-going 7th floor

Lumiere Residences

Building completion:

  • East Tower: October 2018
  • West Tower:  June 2019
  • North Tower: November 2020
Lumiere Residences September 2015 Construction update
Lumiere Residences September 2015 Construction update

Viera Residences

Building completion: March 2018

Viera Residences November 2015 Construction udpdate: Structural Works: 63.55% on-going structural works at 16th floor; Masonry Works: 12.75% complete
Viera Residences November 2015 Construction udpdate: Structural Works: 63.55% on-going structural works at 16th floor; Masonry Works: 12.75% complete

Brio Tower

Building completion: November 2019

Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1

Sheridan Towers

Building completion:

  • South Tower -November 2018
  • North Tower -February 2020
Sheridan Towers November 2015 Construction update: Over-all construction status of the site- 43 %. Structural Work (South Tower): Parking 5 to Parking 1 (100%), Ground Floor (90%), 2nd-28th Floor (100%), 29th Floor-(80%), 30th Floor- (20%).
Sheridan Towers November 2015 Construction update: Amenity Core (South Tower): 50%. Podium ( North Tower) : 20%.

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.

Other DMCI Homes’ resort-type projects:

Previous post

David M. Consunji receives Asia CEO Awards 2015

Next post

DMCI Homes Preselling Projects | December 2015 Construction Updates