DMCI Homes Preselling Projects | September 2015 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

Verawood Residences

Building completion: November 2015

Verawood Residences September 2015 Construction update: Overall : 70.06%. ; MARSALA (left) : 97.57%. All floors completed. On-going QMD acceptance. On-going dress up of units. ; PERIDOT (middle) : 88.00%. All floors completed. On-going bare unit acceptance 2nd flr.. ; CANARY (right) : 55.24%. All floors completed. On-going masonry works upper ground floor.
Verawood Residences September 2015 Construction update: AQUA : 49.87%. All floors completed. Structural works completed. On-going masonry 6th floor.
Verawood Residences September 2015 Construction update: FLAMINGO : 49.62%. All floors completed. Structural works completed.
Verawood Residences September 2015 Construction update: LIME : 45.91%. All floors completed. Structural works completed. On-going exterior masonry works.

One Castilla Place

Building completion: January 2016

One Castlla Place September 2015 Construction update: Structural Works: 100% complete; Masonry Works: 99% complete; Finishing Works: 83.15% complete
One Castlla Place September 2015 Construction update: Swimming Pool: 96.19% complete
One Castlla Place September 2015 Construction update: Swimming Pool: 96.19% complete
One Castlla Place September 2015 Construction update: Drop-off lobby

Outlook Ridge Residences

Building completion: June 2016

Outlook Ridge Residences September 2015 Construction update: South Wing – 59.14%. 7/7 Levels are already concreted.
Outlook Ridge Residences September 2015 Construction update: South Wing – 59.14%. 7/7 Levels are already concreted.
Outlook Ridge Residences September 2015 Construction update
Outlook Ridge Residences September 2015 Construction update: Atrium

Levina Place

Building completion:

  • Selene Building – October 2016
  • Callista Building – July 2016
  • Amalthea Building – Feb 2017
Levina Place September 2015 Construction update: Selene building
Levina Place September 2015 Construction update: Callista building
Levina Place September 2015 Construction update: Clubhouse
Levina Place September 2015 Construction update: Lap Pool
Levina Place September 2015 Construction update: Amenity Area
Levina Place September 2015 Construction update: Amalthea

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
The Birchwood September 2015 Construction update: Guardhouse: 82.50%. On-going finishing works.
The Birchwood September 2015 Construction update: Guardhouse: Over-all construction status of the site : 22.06%.
The Birchwood September 2015 Construction update: Evergreen : 21.30%. On going structural works at 5F.
The Birchwood September 2015 Construction update: Evergreen : Alder : 33.75%. On-going structural works at Roof Deck; On-going masonry works at UGF.
The Birchwood September 2015 Construction update:  Oleander : 10.80%. On going structural works at 3F.
The Birchwood September 2015 Construction update: Maple : 6.00%. On going structural works at PL1. ; Calathea : 5.10%. On going structural works at PL1.

Mirea Residences

Building completion:

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – February 2018
  • Selenia – August 2018
  • Solana – February 2019
  • Antara – TBA
  • Marinda – TBA
  • Aleia – TBA
Mirea Residences September 2015 Construction update: Entrance / Guardhouse : 12.88%
Mirea Residences September 2015 Construction update: Maia : 18.19%. UGF slab – 100%
Mirea Residences September 2015 Construction update: Sitara : 9.87%. Lower level 1 slab – 100%.
Mirea Residences September 2015 Construction update: Aleia : 5.02%. Pile driving – 100%.
Mirea Residences September 2015 Construction update: Marinda : 4.61%. Pile driving – 100%.

Zinnia Towers

Building completion:

  • North Tower: May 2016
  • South Tower: September 2017
Zinnia Towers September 2015 Construction update: North Tower: Masonry Works 93% complete- On-going CHB laying and plastering at 40th floor; Finishing Works: 78% complete- Turnover of bare units at 23rd floor.
Zinnia Towers September 2015 Construction update: South Tower: Structural Works 30.61% completed- On-going 14th floor Area 2; Masonry Works: 10.20% completed- Balcony and EE, Aux room-6th floor
Zinnia Towers September 2015 Construction update: Sky Park: On-going punch listing works
Zinnia Towers September 2015 Construction update: Sky Park: On-going punch listing works
Zinnia Towers September 2015 Construction update: Sky Park: On-going punch listing works
Zinnia Towers September 2015 Construction update: Amenity area

Lumiere Residences

Building completion:

  • East Tower: October 2018
  • West Tower:  June 2019
  • North Tower: November 2020
Lumiere Residences September 2015 Construction update
Lumiere Residences September 2015 Construction update

Viera Residences

Building completion: March 2018

Viera Residences September 2015 Construction update: Structural Works: 41.85% complete; Masonry Works: 9.25% complete; Over-all project accomplishment: 25.35% complete

Brio Tower

Building completion: November 2019

Brio Tower September 2015 Construction update: Structural Works: ongoing Basement 5. Excavation Works: 100% completed

Sheridan Towers

Building completion:

  • South Tower -November 2018
  • North Tower -February 2020
Sheridan Towers September 2015 Construction update: Over-all construction status of the site- 41 %. Structural Work (South Tower): Parking 5 to Parking 1 (100%), Ground Floor (90%), 2nd-23rd Floor (100%), 24th Floor (50%).
Sheridan Towers September 2015 Construction update: Amenity Core (South Tower): 50%. Podium ( North Tower) : 11%.

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.