DMCI Homes Preselling Projects | December 2015 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

Verawood Residences

Building completion: November 2015

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
Verawood Residences December 2015 construction update: Wisteria building: 100%. All floors completed. Accepted by QMD. Dressed up all units. Marsala building: 99.55%. All floors completed. Accepted by QMD. On-going dress up of units.
Verawood Residences December 2015 construction update: Peridot building: 95.97%. All floors completed. On-going QMD acceptance. On-going dress up of units. Canary building: 75.62%. All floors completed. On-going bare units and finishing works.
Verawood Residences December 2015 construction update: Aqua building (left):56.80%. All floors completed. On-going masonry works. Lime building (right): 47.34% All floors completed. Structural works completed. Exterior canopy works. CLUBHOUSE (middle): 96.83%. Accepted by QMD. AMENITIES: 99.21%. Accepted by QMD.
Verawood Residences December 2015 construction update: Flamingo building: 50.20%. All floors completed. Structural works completed. On-going elevator shaft enclosure.

One Castilla Place

Building completion: January 2016

One Castilla Place December 2015 construction update: Finishing Works: 86.57%; Basement levels and 16 floors on-going finishing works.
One Castilla Place December 2015 construction update
One Castilla Place December 2015 construction update
One Castilla Place December 2015 construction update

Outlook Ridge Residences

Building completion: June 2016

  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, BRISTLE RIDGE, the newest mid-rise preselling development similar to OUTLOOK RIDGE RESIDENCES in Baguio is now open for selling!
Outlook Ridge Residences December 2015 construction update
Outlook Ridge Residences December 2015 construction update: South Wing Roofdeck. South Wing: 70.16%. 7/7 Levels are already concreted; 7/7 Levels done for masonry works, ongoing finishing works.
Outlook Ridge Residences December 2015 construction update: North Wing Roofdeck. North Wing: 94.68%. 7/7 Levels are concreted; 7/7 levels done for masonry works, ongoing finsihing works.

Levina Place

Building completion:

  • Selene Building – October 2016
  • Callista Building – July 2016
  • Amalthea Building – Feb 2017
Levina Place October 2015 Construction update
Levina Place October 2015 Construction update
Levina Place October 2015 Construction update

The Birchwood

Building completion:

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
  • All units are sold out. But not to worry, DMCI Homes understands the needs of our clients, reason why, IVORY WOOD and MAPLE PLACE, the 2 newest mid-rise preselling developments similar to Verawood Residences in Taguig are now open for selling!
The Birchwood December 2015 Construction update: Over-all construction status of the site : 32.29%
The Birchwood December 2015 Construction update: Alder : 45%. On-going Masonry Works at Exterior and Atrium; On-going MEPF Works.
The Birchwood December 2015 Construction update: Evergreen : 40.00%. On-going Masonry works at Elevator Deck (Parapet Wall).
The Birchwood December 2015 Construction update: Clubhouse – 15%. On-going structural works at Level 2.
The Birchwood December 2015 Construction update: OLEANDER – 25%. On-going structural works at Parapet Wall – Suspended Slab and Columns; On-going installation of formworks at Parapet Wall. ; MAPLE – 8%. On-going Structural Works at UGF – Columns and Slabs. ; CALATHEA – 8%. On-going structural works at LGF (Columns and Suspended Slab).

Asteria Residences

Building completion:

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
  • Lucerne – April 2018
  • Begonia – June 2018
  • Heather -TBA
  • Cercis – TBA
Asteria Residences Heather building December 2015 Construction update: Overall Structural Works = 3.25%
Asteria Residences Lucerne building December 2015 Construction update: Overall Structural Works = 11%
Asteria Residences Begonia building December 2015 Construction update: Overall Structural Works = 6.25%

Mirea Residences

Building completion:

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – February 2018
  • Selenia – August 2018
  • Solana – February 2019
  • Antara – TBA
  • Marinda – TBA
  • Aleia – TBA
Mirea Residences October 2015 Construction update
Mirea Residences October 2015 Construction update

Zinnia Towers

Building completion:

  • North Tower: May 2016
  • South Tower: September 2017
Zinnia North Tower November 2015 Construction update: Masonry Works 90.71% complete; On-going punchlist works at 38th floor; Finishing Works 70.45% complete; Turn Over Group acceptance of bare units at 37th floor
Zinnia South Tower Novemebr 2015: Structural Works 38.78% on-going 19th floor; Masonry Works: 3.05% on-going 7th floor

Lumiere Residences

Building completion:

  • East Tower: October 2018
  • West Tower:  June 2019
  • North Tower: November 2020
Lumiere Residences December 2015 Construction update

Viera Residences

Building completion: March 2018

Viera Residences December 2015 Construction update: Structural Works: 66.25%; Masonry Works: 16.85%

Brio Tower

Building completion: November 2019

Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1
Brio Tower November 2015 Construction update: Structural Works (Substructure): 86.65% complete; On-going structural and concreting works at Basement level 1

Sheridan Towers

Building completion:

  • South Tower -November 2018
  • North Tower -February 2020
Sheridan Towers December 2015 construction update: Over-all construction status of the site- 45 %. Structural Work (South Tower): Parking 5 to Parking 1 (100%), Ground Floor (90%), 2nd-31st Floor (100%), 32nd (80%), 33rd Floor- (10%). Amenity Core (South Tower): 50% . Podium ( North Tower) : 25% .

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.

Other DMCI Homes’ resort-type projects:

Previous post

DMCI Homes Preselling Projects | November 2015 Construction Updates

Next post

Season's greetings from www.getdmci.com