DMCI Homes Preselling Projects | June 2015 Construction Updates

Stay posted on the latest updates on DMCI Homes Pre-selling projects. Top developer always gives updates on your investments!

One Castilla Place

Building completion

  • January 2016
One Castilla Place June 2015 Construction update
One Castilla Place June 2015 Construction update: Pool Deck: 85% complete
One Castilla Place June 2015 Construction update: Ground Floor Open Lounge: 92% complete
One Castilla Place June 2015 Construction update: Guard house: 7% complete

Outlook Ridge Residences

Building completion

  • June 2016

Over-all Site Development – 73%. North Wing – 61.82%.

Outlook Ridge Residences June 2015 Construction update: North Wing – 61.82%.
Outlook Ridge Residences June 2015 Construction update: North Wing – 7/7 Levels are concreted.
Outlook Ridge Residences June 2015 Construction update: South Wing – 50.86%.
Outlook Ridge Residences June 2015 Construction update: South Wing – 7/7 Levels are already concreted.

Zinnia Towers

Building completion

  • North Tower – May 2016
  • South Tower – September 2017

North Tower: 75% complete. On-going finishing works at 26th floor; South Tower: 14% complete. On-going structural works at 6th floor; Site Development and Amenities: Clubhouse completed; North Tower amenities on-going finishing works.

Zinnia Towers June 2015 Construction update
Zinnia Towers June 2015 Construction update: North Tower: 75% complete. On-going finishing works at 26th floor
Zinnia Towers June 2015 Construction update: South Tower: 14% complete. On-going structural works at 6th floor
Zinnia Towers June 2015 Construction update: te Development and Amenities: Clubhouse completed; North Tower amenities on-going finishing works
Zinnia Towers June 2015 Construction update: te Development and Amenities: Clubhouse completed; North Tower amenities on-going finishing works
Zinnia Towers June 2015 Construction update: te Development and Amenities: Clubhouse completed; North Tower amenities on-going finishing works

Asteria Residences

Building completion

  • Nerine – April 2017
  • Vinca – July 2017
  • Mimosa – January 2018
Asteria Residences June 2015 Construction update: Vinca Building is 11% complete.
Asteria Residences June 2015 Construction update: Nerine Building is 11% complete.

Mirea Residences

Building completion

  • Maia – August 2017
  • Sitara – August 2017
  • Vespera – August 2018
  • Solana – February 2019
MAIA – Column at Lower Level 1. Pile Driving – 100%, Substructure-100%, Superstructure-6.19%. SITARA – Column at Lower Level 2. Superstructure-4.58%. VESPERA – Slab on Grade. Pile Driving and Substructure – 100%.
ALEIA – 13.08%(pile driving) ; MARINDA – 100%(pile driving) ; ANTARA – 100%(pile driving) ; SOLANA – 100%(pile driving). ; SELENIA – 64.58%(substructure). Footing tie beam and starter column.
Entrance walkway

The Birchwood (Sold out)

Building completion

  • Alder – December 2016
  • Evergreen – March 2017
  • Oleander – September 2017
  • Maple – January 2018
  • Calathea – January 2018
Over-all site development: 17.78%. Clubhouse: 9%. On-going rebar works and concreting at LGF. CALATHEA building: 6.60%. On-going rebar works for columns and concreting for SOG at Parking Level 2. MAPLE building : 6.60%. On-going concreting of Columns at Parking Level 2.
ALDER building: 26.40%. On going concreting of Suspended Slabs at 6F.
Guardhouse: 80%. On-going finishing works.
EVERGREEN building : 8.10%. On-going concreting of Columns at LGF. OLEANDER building : 7.80%. On-going concreting of suspended slabs at LGF.

Viera Residences

Building completion

  • March 2018

Over all project accomplishment: 18.65% complete.

Viera Residences June 2015 Construction update: Over all project accomplishment: 18.65% complete.
Viera Residences June 2015 Construction update: Over all project accomplishment: 18.65% complete.

Brio Tower

Building completion: August 2019

Brio Tower June 2015 Construction update: Structural Works: 42.52% complete.
Brio Tower June 2015 Construction update: Excavation Works: 85% complete.

Sheridan Towers

Building completion:

  • South Tower – August 2018
  • North Tower – February 2020

Over-all construction status of the site- 29.29%.

Sheridan Towers June 2015 Construction update: Over-all construction status of the site- 29.29%.
Sheridan Towers June 2015 Construction update: Over-all construction status of the site- 29.29%.

Send us a message!

If you have any questions, want to meet up, or need more information, send us a message.

Other DMCI Homes’ resort-type projects:

Previous post

Construction progressing in Zinnia Towers, Quezon City

Next post

DMCI Homes Preselling Projects | July 2015 Construction Updates